LH boneless apartment status

image text translation

(1)This is a guide to the occupants
(2)After the collapse of the underground parking lot in the Geomdan district of Incheon, LH inspected LH construction sites and residential complexes nationwide and conducted a sampling non-destructive inspection of 16 underground parking lot columns in the Byeolla First Forest Complex, and found that shear reinforcement reinforcement was missing at 15 locations
(3)There was no abnormality in the drawings provided by LH to the construction company, but due to the negligence of the construction company and the supervisor, the strength of the concrete specimen was confirmed at the time of construction. Unlike the collapse of the underground parking lot at the Incheon Prosecutor’s Office, it was confirmed that the concrete strength of the underground parking lot satisfies the design strength or the height of the soil load on the upper part of the parking lot is within the design load range, and the safety rate of the design strength has not caused any problems so far
(4)LH plans to urgently push for a precise safety diagnosis in consultation with tenants as soon as possible to determine the final scope of reinforcement measures, and the construction company will carry out emergency reinforcement work for residents’ safety as follows before the diagnosis results are released
(5)LH Precision Safety Diagnostics Request and Implementation of Precision Safety Diagnosis to External Agencies
(6)About 10 days from the start of the field investigation period, about one month from the start of the comprehensive investigation period, the schedule of the investigation results, etc. will be informed later
(7)Estimated number of people surveyed is around 6
(8)※ If the reinforcement plan is confirmed after diagnosis, the residents will be informed of the safety compared to the original design
(9)Construction Reinforcement Construction Installation of temporary support for the first reinforcement of some columns, such as the lower part of an emergency lane, apart from the above precise safety diagnosis
(10)- Start after consultation on lease for approximately one month from the commencement date of the estimated construction period – adjust the completion time
(11)· 22 pillars located on the 1st basement floor of the pillar subject to reinforcement
(12)Provision of parking lots in nearby shopping malls for the phased reinforcement of alternative parking spaces Additional nearby land for the entire simultaneous construction
(13)We will continue to discuss compensation for damage to residents, and we inform you that the supervisory company will bear the costs incurred if you request other specialized organizations directly to verify precision safety diagnosis and reinforcement work
(14)We sincerely apologize for the above news, and we are very sorry for the anxiety and inconvenience caused by the reinforcement work. This is a measure for a safer apartment complex, so we ask for your understanding and cooperation
(15)LH Gyeonggi Northern Headquarters

httpswwwenewstodaycokrnewsarticleViewhtmlidxno=2058425

It didn’t take long after the announcement was made

You said it’s not convenient to inspect this complex unlike other complexes

blanking out the scrutiny

Leave a Comment